CONSTRUCTION HOURS:
  • Friday, October 31, 2014: 3am – 8pm (North & West) /  3am – 3pm/3pm – 3am (East) 
  • Saturday, November 1, 2014: 2am – 8pm (North) / 4am – 6pm (West) / 3am – 3pm/3am – 3pm (East) / 7am – 7pm (N2)
  • Sunday, November 2, 2014: 8am – 6pm (North) / 6am – 3pm (West) / 3am – 3pm/3pm – 3am) (East) / 7am – 7pm (N2)
  • Monday, November 3, 2014: 3am – 3pm/3pm – 3am (East & West) / 12am – 3pm/3pm – 3am (North) / 7am – 7pm (N2)
CONSTRUCTION ACTIVITIES:
  • Vertical and Slab Pours (All Blocks) / as needed
  • Structural Steel Erection (All Blocks)
  • Excavation and Trucking ( All Blocks) 
  • Security and Monitoring (All Blocks / everyday)
CLOSURES:
  • Full road closure:  South Miami Avenue between 7th and 8th Streets
    • 4am, Saturday, November 1, 2014 – 5.30am, Monday, November 3, 2014
  • Monday – Friday / 9.30am – 3.30pm / as needed
    • Single lane closure: South Miami Avenue, between 7th and 6th Streets
    • Single/Double Lane closure: SW/SE 8th Street
  • Sunday – Thursday / 9pm – 5.30am / as needed
    • Double Lane Closure: SE 7th Street & SW/SE 8th Street
    • Single Lane Closure: SE 6th Street 
  • Saturday & Sunday / 6am – 4pm / as needed
    • Single/Double Lane Closure: SW/SE 7th Street
    • Single/Double Lane Closure: SE/SW 8th Street
LANE & SIDEWALK CLOSURES:
  • South Miami Avenue (East Lane) from SE 8th Street to SE 6th Street
  • SW 7th Street, SE/SW 8th Street,  SE 6th Street, and South Miami Avenue.
  • Temporary Sidewalk Closure: SW 8th Street / South Side between SW 1st Ave and South Miami Ave.
PLEASE NOTE THE MAP DOES NOT REFLECT ALL CLOSURES. REFER TO THE ABOVE DESCRIPTIONS FOR UP-TO-DATE CLOSURES.